Highways England will be carrying out work at the above location to replace the expansion joints and re-waterproof the Junction 9 overbridge. We will also be carrying out some resurfacing.
We plan to complete this work over 13 weeks from Thursday 16 September to Monday 13 December, subject to weather conditions.
Closures and diversions
We have liaised with the local authority to agree the most suitable dates and diversion routes for this work which is as follows:
Northbound closures
- M11 junction 8 to 10 northbound full closure
Thursday 16 September to Sunday 20 September – 10pm to 5am
Thursday 14 October – 10pm to 5am
Thursday 11 November – 10pm to 5am
Friday 3 December to Sunday 5 December – full weekend closure
- M11 junction 9 to 10 northbound single lane closure
Friday 17 September to Wednesday 13 October – 24 hours
Friday 15 October to Thursday 11 November – 24 hours
Northbound traffic will be diverted off the M11 at junction 8 onto the A120, A10 and the A505 and re-join the M11 at junction 10.
Southbound closures
- M11 J10 – J9 Southbound Carriageway full closure
Thursday 14 October – 10pm to 5am
Thursday 11 November – 10pm to 5am
Thursday 2 December – 10pm to 5am
Friday 10 December to Monday 13th December – Full Weekend Closure
- M11 J10 – J9 Southbound single lane closure
Friday 15 October to Thursday 11 November – 24 hours
Friday 12 November to Thursday 2 December – 24 hours
Southbound traffic will be diverted off the M11 at junction 10 onto the A505, A1301 and re-join the M11 from junction 9a to junction 9.